21 July 2014

News Story: India's 20-Year Late LCA Faces Fresh Delays

Tejas LCA Fighter (File Photo)

By VIVEK RAGHUVANSHI

NEW DELHI — India’s Light Combat Aircraft (LCA) Mark-1, already 20 years late, likely will miss its final operational clearance (FOC) deadline set for the end of 2014, an Indian Air Force source said.

In the run-up to the FOC stage, handling tests are being performed on only one aircraft while the remaining five are still in production. Ideally, handling flight tests should be performed on at least six aircraft to ascertain their operational readiness, the source said.

“With handling tests on only one aircraft, and the remaining not even manufactured, it is impossible to get FOC by December’s end,” the source said.

The initial operational clearance (IOC) for LCA Mark-1 was received in December. Now the aircraft must demonstrate full performance as defined by the design and agreement of the Indian Air Force.

Read the full story at DefenseNews